SPF DMS
Help Material
×
Menu
Index

Creating a Turnover Dossier

Turnover Dossiers are created from the action menu of a sub-system.  There are some important pre-requisites before the option becomes available:
1.     Sub-system must be related to a Contract
2.     The Sub-system’s contract must have been awarded to a contractor which is determined by the _V package of the contract being related to an organization
3.     At least one SPF document must reference the sub-system
4.     A turnover dossier must not already exist for the sub-system
5.     The command is available only to Field Engineers (FE), Field Engineering Managers (FEM), Sub-system Scope Coordinators and Commissioning Managers
Once all pre-requisites have been fulfilled the sub-system will show the option to create a Turnover Dossier from the Action Menu of the Sub-system: Action Menu -> Create Turn Over Dossiers
 
 
Important:
Creating a dossier is an intensive process and can take several minutes to complete.