Turnover Dossiers gather information from SPF, SC, and Share Point into a collection of information to be turned over from construction to commissioning.
The collection is based on the commissioning sub-system such that only information pertaining (related to) a specific sub-system will be included as part of the relevant turnover dossier. The content to include was defined per dossier chapter as shown below.
Section/Chapter
|
Explanation
|
Base Criteria
|
Scoped Drawings
|
|
|
PFDs
|
Documents of the sub-system including those inferred by tags where the DWG Type = PFD.
The revisions must be CURRENT IFC and issued to a contractor to be included. (As Built Markup and As Built Redline have also been included)
|
DWG Type = PFD
|
P&IDs
|
Documents of the sub-system including those inferred by tags where the DWG Type = PID.
The revisions must be CURRENT IFC and issued to a contractor to be included. (As Built Markup and As Built Redline have also been included)
|
DWG Type = PID
|
SLDs
|
Documents of the sub-system including those inferred by tags where the disciplne = EL and document type = ESL or ESS.
The revisions must be CURRENT IFC and issued to a contractor to be included. (As Built Markup and As Built Redline have also been included)
|
EL-ESL, EL-ESS
|
IBDs
|
Documents of the sub-system including those inferred by tags where the DWG Type = IBD.
The revisions must be CURRENT IFC and issued to a contractor to be included. (As Built Markup and As Built Redline have also been included)
|
DWG Type = IBD
|
Other
|
Document revisions are manually associated to this chapter
|
N/A
|
Section/Chapter
|
Explanation
|
Base Criteria
|
Status
|
|
|
Civil Checksheets
|
SC checksheets for civil tags in the sub-system
|
N/A
|
Structural Checksheets
|
SC checksheets for structural tags in the sub-system
|
N/A
|
Electrical Checksheets
|
SC checksheets for electrical tags in the sub-system
|
N/A
|
Mechanical Checksheets
|
SC checksheets for mechanical tags in the sub-system
|
N/A
|
Instrumentation & Controls Checksheets
|
SC checksheets for I&C tags in the sub-system
|
N/A
|
Piping Checksheets
|
SC checksheets for piping tags in the sub-system
|
N/A
|
Safety & Control Checksheets
|
SC checksheets for safety & control tags in the sub-system
|
N/A
|
Loose Items Sign Off
|
Documents of the sub-system excluding those inferred by tags where the discipline is CT and document type = LST and VDRL Code = G09
|
CT-LST and VDRL = G09
|
Preservations Records
|
SC preservation records for tags in the sub-system
|
N/A
|
Final Walk Down Attendance
|
Documents of the sub-system excluding those inferred by tags where the discipline is CT and document type = MOM
|
CT-MOM
|
Punchlist
|
SC punchlist items for the sub-system
|
N/A
|
Construction TQs
|
SPF Construction TQs related to the sub-system
|
N/A
|
NCRs
|
Document revisions are manually associated to this chapter
|
N/A
|
MOC (Temporary Alteration List)
|
SC MOC for the sub-system
|
N/A
|
Section/Chapter
|
Explanation
|
Base Criteria
|
Vendor and Statutory Items
|
Documents of the sub-system excluding those inferred by tags where the discipline is CT and document type = RPT or the document type = PER or the document type = LEM
|
CT-RPT or
doc type = PER or doc type = LEM
|
|
|
|
Redlines
|
|
|
Redline Index
|
Documents of the sub-system excluding those inferred by tags where the discipline is CT and document type = RGT
|
CT-RGT
|
Redlines
|
SPF Redlines related to the sub-system
|
N/A
|