Submitting a Turnover Dossier for ApprovalContractors can submit the Turnover Dossier by using the submit command for Turnover Dossiers with a status of Draft.
Note:
The following documents should be signed-off, CURRENT per the standard document life-cycle before the dossier is submitted otherwise, it will be returned to the submitter for correction. The submitter can re-submit the turnover dossier once they have coordinated to have the information signed off:
· Scope Drawings
· Loose Items Sign Off
· Final Walkdown Attendance
· Vendor and Statutory Items
· Redline Index
|